New kitchen, economy grade ($4k - $6k)
A kitchen renovation will typically take between 2 to 3 weeks to complete.
Demolition and rough-in for plumbing and electrical circuits
Kitchen cabinetry fabrication can take 1 to 4 weeks depending on the backlog of the cabinetry shop.
The kitchen cabinetry can typically be installed in 1 to days. Once the cabinetry is installed the counter top fabricator can field measure the cabinetry and get the measurements for the counter tops. The counter tops will typically take between 1 to 2 weeks to be fabricated.
During the waiting time for the countertops, your Contractor may start installing the tile flooring in the kitchen, or may choose to work elsewhere in the property.
Once the counter tops have been fabricated the tops can typically be installed in 4 to 8 hours.
After the countertops have been installed you can install the tile backsplash 1 to 2 days.
Estimating kitchen costs.